International Monetary Fund
Pakistan: Financial Position in the Fund

Member Financial Data



Pakistan: Projected Payments to the IMF
as of September 30, 2006



Projected charges/interest and due dates are tentative. GRA charges are due two business days following notification to members shortly after quarter end. Net SDR charges and annual SDR assessments are due on the first day after the end of the quarter and April 30, respectively. RST interest is due promptly after the end of the quarter.

Download this file
TSV -- TSV tips

(in SDRs)
Description Schedule Date Total
Amount Due
PRGT Repayment (ECF)  October 13, 200611,373,000
GRA Repurchase (EFF)  October 20, 20063,159,167
Net SDR Charges  November 01, 2006227,014
GRA Charges  November 01, 2006547,158
PRGT Repayment (ECF)  November 03, 200611,373,000
GRA Repurchase (EFF)  December 01, 20063,159,167
PRGT Interest 1/  December 31, 20062,399,437
Total for the year 200632,237,943
 
GRA Repurchase (EFF)  January 19, 20071,580,833
PRGT Repayment (ECF)  January 26, 20073,791,000
GRA Charges  February 01, 2007467,010
Net SDR Charges  February 01, 2007229,651
GRA Repurchase (EFF)  March 30, 20071,579,167
PRGT Repayment (ECF)  April 13, 200711,373,000
GRA Repurchase (EFF)  April 20, 20073,159,167
SDR Assessments  April 30, 20079,517
GRA Charges  May 01, 2007409,276
Net SDR Charges  May 01, 2007222,162
PRGT Repayment (ECF)  May 03, 200711,373,000
GRA Repurchase (EFF)  June 01, 20073,159,167
PRGT Repayment (ECF)  June 19, 20078,616,000
PRGT Interest 1/  June 30, 20072,292,824
GRA Repurchase (EFF)  July 19, 20071,580,833
PRGT Repayment (ECF)  July 27, 20073,791,000
GRA Charges  August 01, 2007342,991
Net SDR Charges  August 01, 2007229,651
GRA Repurchase (EFF)  October 01, 20071,579,167
PRGT Repayment (ECF)  October 09, 20078,614,000
PRGT Repayment (ECF)  October 12, 200711,373,000
GRA Repurchase (EFF)  October 22, 20073,159,163
Net SDR Charges  November 01, 2007229,651
GRA Charges  November 01, 2007299,689
PRGT Repayment (ECF)  November 02, 200711,373,000
GRA Repurchase (EFF)  November 30, 20073,159,167
PRGT Repayment (ECF)  December 19, 20078,616,000
PRGT Interest 1/  December 31, 20072,232,135
Total for the year 2007104,841,221
 
GRA Repurchase (EFF)  January 18, 20081,580,833
PRGT Repayment (ECF)  January 22, 20088,614,000
PRGT Repayment (ECF)  January 28, 20083,791,000
GRA Charges  February 01, 2008217,211
Net SDR Charges  February 01, 2008229,651
GRA Repurchase (EFF)  April 01, 20081,579,163
PRGT Repayment (ECF)  April 09, 20088,614,000
PRGT Repayment (ECF)  April 14, 200811,373,000
SDR Assessments  April 30, 20089,517
GRA Charges  May 01, 2008175,414
Net SDR Charges  May 01, 2008224,659
PRGT Repayment (ECF)  May 16, 20088,614,000
GRA Repurchase (EFF)  May 30, 20083,159,167
PRGT Repayment (ECF)  June 19, 20088,616,000
PRGT Interest 1/  June 30, 20082,078,389
GRA Repurchase (EFF)  July 18, 20081,580,833
PRGT Repayment (ECF)  July 22, 20088,614,000
PRGT Repayment (ECF)  July 28, 20083,791,000
GRA Charges  August 01, 2008134,043
Net SDR Charges  August 01, 2008229,651
PRGT Repayment (ECF)  September 16, 20088,614,000
PRGT Repayment (ECF)  October 09, 20088,614,000
GRA Charges  November 01, 2008103,449
Net SDR Charges  November 01, 2008229,651
PRGT Repayment (ECF)  November 17, 20088,614,000
GRA Repurchase (EFF)  December 01, 20083,159,167
PRGT Repayment (ECF)  December 19, 20088,616,000
PRGT Interest 1/  December 31, 20081,976,061
PRGT Repayment (ECF)  December 31, 20088,614,000
Total for the year 2008121,765,859
 
GRA Repurchase (EFF)  January 19, 20091,580,837
PRGT Repayment (ECF)  January 22, 20098,614,000
PRGT Repayment (ECF)  January 28, 20093,791,000
Net SDR Charges  February 01, 2009229,651
GRA Charges  February 01, 200972,691
PRGT Repayment (ECF)  March 16, 20098,614,000
PRGT Repayment (ECF)  April 09, 20098,614,000
SDR Assessments  April 30, 20099,517
GRA Charges  May 01, 200940,133
Net SDR Charges  May 01, 2009222,162
PRGT Repayment (ECF)  May 12, 200917,228,000
PRGT Repayment (ECF)  May 15, 20098,614,000
GRA Repurchase (EFF)  June 01, 20093,159,163
PRGT Repayment (ECF)  June 19, 20098,616,000
PRGT Repayment (ECF)  June 30, 20098,614,000
PRGT Interest 1/  June 30, 20091,799,398
PRGT Repayment (ECF)  July 22, 20098,614,000
GRA Charges  August 01, 200913,979
Net SDR Charges  August 01, 2009229,651
PRGT Repayment (ECF)  September 16, 20098,614,000
PRGT Repayment (ECF)  October 09, 20098,614,000
Net SDR Charges  November 01, 2009229,651
PRGT Repayment (ECF)  November 12, 200917,228,000
PRGT Repayment (ECF)  November 17, 20098,614,000
PRGT Repayment (ECF)  December 18, 20098,616,000
PRGT Interest 1/  December 31, 20091,654,621
PRGT Repayment (ECF)  December 31, 20098,614,000
Total for the year 2009150,860,454
 
PRGT Repayment (ECF)  January 08, 201017,228,000
PRGT Repayment (ECF)  January 22, 20108,614,000
Net SDR Charges  February 01, 2010229,651
PRGT Repayment (ECF)  March 16, 20108,614,000
PRGT Repayment (ECF)  April 09, 20108,614,000
SDR Assessments  April 30, 20109,517
Net SDR Charges  May 01, 2010222,162
PRGT Repayment (ECF)  May 12, 201017,228,000
PRGT Repayment (ECF)  May 17, 20108,614,000
PRGT Repayment (ECF)  June 18, 20108,616,000
PRGT Interest 1/  June 30, 20101,415,311
PRGT Repayment (ECF)  June 30, 20108,614,000
PRGT Repayment (ECF)  July 09, 201017,228,000
PRGT Repayment (ECF)  July 22, 20108,614,000
Net SDR Charges  August 01, 2010229,651
PRGT Repayment (ECF)  September 16, 20108,614,000
PRGT Repayment (ECF)  October 08, 20108,614,000
Net SDR Charges  November 01, 2010229,651
PRGT Repayment (ECF)  November 12, 201017,228,000
PRGT Repayment (ECF)  November 17, 20108,614,000
PRGT Repayment (ECF)  December 17, 20108,616,000
PRGT Interest 1/  December 31, 20101,222,023
PRGT Repayment (ECF)  December 31, 20108,614,000
Total for the year 2010175,841,966
 
PRGT Repayment (ECF)  January 07, 201117,228,000
PRGT Repayment (ECF)  January 21, 20118,614,000
Net SDR Charges  February 01, 2011229,651
PRGT Repayment (ECF)  March 16, 20118,614,000
PRGT Repayment (ECF)  April 08, 20118,614,000
SDR Assessments  April 30, 20119,517
Net SDR Charges  May 01, 2011222,162
PRGT Repayment (ECF)  May 12, 201117,228,000
PRGT Repayment (ECF)  May 17, 20118,614,000
PRGT Repayment (ECF)  June 17, 20118,616,000
PRGT Repayment (ECF)  June 30, 20118,614,000
PRGT Interest 1/  June 30, 2011987,552
PRGT Repayment (ECF)  July 08, 201117,228,000
PRGT Repayment (ECF)  July 22, 20118,614,000
Net SDR Charges  August 01, 2011229,651
PRGT Repayment (ECF)  September 16, 20118,614,000
PRGT Repayment (ECF)  October 07, 20118,614,000
Net SDR Charges  November 01, 2011229,651
PRGT Repayment (ECF)  November 11, 201117,228,000
PRGT Repayment (ECF)  November 17, 20118,614,000
PRGT Repayment (ECF)  December 19, 20118,616,000
PRGT Repayment (ECF)  December 30, 20118,614,000
PRGT Interest 1/  December 31, 2011787,301
Total for the year 2011174,979,485
 
PRGT Repayment (ECF)  January 09, 201217,228,000
PRGT Repayment (ECF)  January 20, 20128,614,000
Net SDR Charges  February 01, 2012229,651
PRGT Repayment (ECF)  March 16, 20128,614,000
PRGT Repayment (ECF)  April 09, 20128,614,000
SDR Assessments  April 30, 20129,517
Net SDR Charges  May 01, 2012224,659
PRGT Repayment (ECF)  May 11, 201217,228,000
PRGT Repayment (ECF)  May 17, 20128,614,000
PRGT Repayment (ECF)  June 29, 20128,614,000
PRGT Interest 1/  June 30, 2012563,911
PRGT Repayment (ECF)  July 09, 201217,228,000
PRGT Repayment (ECF)  July 20, 20128,614,000
Net SDR Charges  August 01, 2012229,651
PRGT Repayment (ECF)  September 14, 20128,614,000
Net SDR Charges  November 01, 2012229,651
PRGT Repayment (ECF)  November 12, 201217,228,000
PRGT Repayment (ECF)  November 16, 20128,614,000
PRGT Repayment (ECF)  December 31, 20128,614,000
PRGT Interest 1/  December 31, 2012385,394
Total for the year 2012148,310,434
 
PRGT Repayment (ECF)  January 09, 201317,228,000
Net SDR Charges  February 01, 2013229,651
PRGT Repayment (ECF)  March 15, 20138,614,000
SDR Assessments  April 30, 20139,517
Net SDR Charges  May 01, 2013222,162
PRGT Repayment (ECF)  May 10, 201317,228,000
PRGT Repayment (ECF)  June 28, 20138,614,000
PRGT Interest 1/  June 30, 2013232,814
PRGT Repayment (ECF)  July 09, 201317,228,000
Net SDR Charges  August 01, 2013229,651
Net SDR Charges  November 01, 2013229,651
PRGT Repayment (ECF)  November 12, 201317,228,000
PRGT Interest 1/  December 31, 2013120,360
Total for the year 201387,413,806
 
PRGT Repayment (ECF)  January 09, 201417,228,000
Net SDR Charges  February 01, 2014229,651
SDR Assessments  April 30, 20149,517
Net SDR Charges  May 01, 2014222,162
PRGT Interest 1/  June 30, 201444,604
PRGT Repayment (ECF)  July 09, 201417,228,000
Net SDR Charges  August 01, 2014229,651
Net SDR Charges  November 01, 2014229,651
PRGT Interest 1/  December 31, 20141,888
Total for the year 201435,423,124
 
Net SDR Charges  February 01, 2015229,651
SDR Assessments  April 30, 20159,517
Net SDR Charges  May 01, 2015222,162
Net SDR Charges  August 01, 2015229,651
Net SDR Charges  November 01, 2015229,651
Total for the year 2015920,632
 
Net SDR Charges  February 01, 2016229,651
SDR Assessments  April 30, 20169,517
Net SDR Charges  May 01, 2016224,659
Net SDR Charges  August 01, 2016229,651
Net SDR Charges  November 01, 2016229,651
Total for the year 2016923,129
 
Net SDR Charges  February 01, 2017229,651
SDR Assessments  April 30, 20179,517
Net SDR Charges  May 01, 2017222,162
Net SDR Charges  August 01, 2017229,651
Net SDR Charges  November 01, 2017229,651
Total for the year 2017920,632
 
Net SDR Charges  February 01, 2018229,651
SDR Assessments  April 30, 20189,517
Net SDR Charges  May 01, 2018222,162
Net SDR Charges  August 01, 2018229,651
Net SDR Charges  November 01, 2018229,651
Total for the year 2018920,632
 
Net SDR Charges  February 01, 2019229,651
SDR Assessments  April 30, 20199,517
Net SDR Charges  May 01, 2019222,162
Net SDR Charges  August 01, 2019229,651
Net SDR Charges  November 01, 2019229,651
Total for the year 2019920,632
 
Net SDR Charges  February 01, 2020229,651
SDR Assessments  April 30, 20209,517
Net SDR Charges  May 01, 2020224,659
Net SDR Charges  August 01, 2020229,651
Net SDR Charges  November 01, 2020229,651
Total for the year 2020923,129
 
Net SDR Charges  February 01, 2021229,651
SDR Assessments  April 30, 20219,517
Net SDR Charges  May 01, 2021222,162
Net SDR Charges  August 01, 2021229,651
Net SDR Charges  November 01, 2021229,651
Total for the year 2021920,632
Total 1,038,123,710

1/ On July 14, 2021, the IMF Executive Board approved a modified interest rate setting mechanism which effectively sets interest rates to zero on ECF and SCF through July 2023 and possibly longer, while the interest rate on RCF remains at zero percent, in line with the Executive Board's decision in 2015. Based on these decisions, the following interest rates are assumed beyond July 2023: 0/0/0 percent per annum for the ECF, SCF and RCF respectively. The Executive Board will review the interest rates on concessional lending by end-July 2023 and every two years thereafter.

Short Description Description
Net SDR ChargesSDR Department - Net Charges
GRA ChargesGeneral Resources Account - REGULAR Charges
GRA Repurchase (EFF)Extended Fund Facility Arrangement - Obligation
PRGT Repayment (ECF)Principal - Extended Credit Facility
PRGT InterestInterest - PRG Trust
SDR AssessmentsSDR Department - Member Assessment

Disclaimer
The information provided is for your convenience and is not intended to replace other official IMF reports and statements.